452 St Kilda Road - Project Completion

PROJECT COMPLETION | Prior to the Christmas break we handed over another completed project to happy clients. 452 St Kilda Road included a cladding upgrade spanning 18 levels of a boutique hotel and covering 3700m2.

As part of the project we partnered with Fairview, using their Ecoloop solution to strip out and recycle the aluminium from the original cladding, reducing environmental impacts and waste. 

“With over 4 million sqm of non-compliant cladding needing replaced on buildings throughout Victoria, it was critical for Kapitol to find and implement an environmentally sustainable solution for this project to reduce the amount of building material ending up in landfill. Ecoloop proved to be a great solution”, said Chris Trimble, Senior Project Manager.

The project was completed over 7 months and on time, despite numerous challenges with weather, COVID lockdowns, and working at height over a live street environment.

A big thank you to our team at Kapitol and the contractors who worked with us to deliver this project. As you can see by the photos, the upgraded building façade is sparkling and adds a touch of glamour to the Melbourne skyline. 

Photographer: Glenn Hester

Client: 452 St Kilda Rd Owners Corporation  
Project Manager: Case Meallin
Architect: JMA Architects
Fire Engineer: RED Fire Engineers
Façade Engineer: Inhabit
Building Surveyor: Philip Chun Building Compliance
Quantity Surveyor: Rider Levett Bucknall

Latest News

Projects Won 2024

Project Announcements 2024

Read More
161 Eastern Road | Project Completion Walkthrough

161 Eastern Road | Project Completion Walkthrough

Join our Project Manager's as they walk us through 161 Eastern Road.

Read More
Topping Out | NEXTDC M2 Melbourne Stage 6

Topping Out | NEXTDC M2 Melbourne Stage 6

Earlier this week we celebrated the topping out of Stage 6 at NEXTDC’s M2 Melbourne Data Centre.

Read More
See more news