PROJECT MILESTONE | The team is excited to share that topping out has been completed at stage 3 of our NEXTDC M2 data centre project 🙌
Top out stats: - Volume of concrete poured: 2650 m3
- Precast panels: 63
- Hours worked to date: 67,548.50 hrs
- Internal floor plate: 7,740 m2
- External floor plate: 5120 m2
Congratulations to the hard working project team, consultants, contractors and subbies. They've done a terrific job throughout and we look forward to completing this stage of the project soon.
Top out stats: - Volume of concrete poured: 2650 m3
- Precast panels: 63
- Hours worked to date: 67,548.50 hrs
- Internal floor plate: 7,740 m2
- External floor plate: 5120 m2
Congratulations to the hard working project team, consultants, contractors and subbies. They've done a terrific job throughout and we look forward to completing this stage of the project soon.
Latest News

Project Win - Stage 2 of Hanwha’s H-ACE Facility
Kapitol has been awarded Stage 2 of Hanwha Defence Australia’s Armoured Vehicle Centre of Excellence (H-ACE), a major step in expanding our expertise into the defence sector.

Assemble Sydney Rd Coburg - Project Win
We are thrilled to announce our latest residential project win: the design and construction of 511-537 Sydney Road, Coburg.

Water Testing at Yarra Valley Grammar
Kapitol conducts rigorous water testing at Yarra Valley Grammar to ensure the facade and windows meet strict waterproofing and durability standards.