NEXTDC M3 - 1 Year Progress Update

PROJECT MILESTONE | Want to see what a 12-month build programme for a 15,986 m2 GFA, 4 level, 27MW #datacentre looks like? 

​This week marks 1 year since we began piling at NEXTDC's latest hyper-scale technology campus in West Footscray. ​In just twelve months we've accomplished big things and are nearing project completion.

​This has been a highly complex build which required close collaboration with the best subbies, contractors and consultants in the industry so a big thank you to all involved.

✅ Watch the video below to discover some key facts and figures from this project.

​Timelapse: Capture Point Media

Latest News

Water Testing at Yarra Valley Grammar

Water Testing at Yarra Valley Grammar

Kapitol conducts rigorous water testing at Yarra Valley Grammar to ensure the facade and windows meet strict waterproofing and durability standards.

Read More
Demolition Works at the Lindrum Redevelopment Underway

Demolition Works at the Lindrum Redevelopment Underway 

Kapitol Group, commercial builder, begins demolition on Time & Place’s Lindrum Redevelopment, balancing heritage preservation with urban transformation.

Read More
161 Eastern Road | Project Completion Walkthrough

161 Eastern Road | Project Completion Walkthrough

Join our Project Manager's as they walk us through 161 Eastern Road.

Read More
See more news