We have recently unwrapped the stunning façade at 161 Eastern Road, a milestone the team has worked tirelessly towards. Our client and architect have been actively involved, particularly through the sample approval process, ensuring that every detail met their vision and standards.
One of the standout features of this project is the curved balcony precast. Getting the curves just right required a few prototypes, but the results speak for themselves. Thanks to our collaboration with Visibuild and our dedicated subcontractors, we’ve set a high standard throughout the project.
The sequence of works played a crucial role in the successful execution of the balcony panels. Poured in with the slab, these panels had to be meticulously landed on the deck before each pour. Managing double height formwork areas and jumping the perimeter scaffold the day after the pour were essential to keep the project moving forward safely and efficiently.
One key lesson we've learned is the importance of sequence, sequence, sequence! From completing inspections at supplier yards to the meticulous planning and execution on site, every step has been crucial to our progress.
We couldn't be prouder of the hard work and dedication of our team at 161 Eastern Road. Stay tuned for more updates as we progress towards completion.
One of the standout features of this project is the curved balcony precast. Getting the curves just right required a few prototypes, but the results speak for themselves. Thanks to our collaboration with Visibuild and our dedicated subcontractors, we’ve set a high standard throughout the project.
The sequence of works played a crucial role in the successful execution of the balcony panels. Poured in with the slab, these panels had to be meticulously landed on the deck before each pour. Managing double height formwork areas and jumping the perimeter scaffold the day after the pour were essential to keep the project moving forward safely and efficiently.
One key lesson we've learned is the importance of sequence, sequence, sequence! From completing inspections at supplier yards to the meticulous planning and execution on site, every step has been crucial to our progress.
We couldn't be prouder of the hard work and dedication of our team at 161 Eastern Road. Stay tuned for more updates as we progress towards completion.
Latest News
161 Eastern Road | Project Completion Walkthrough
Join our Project Manager's as they walk us through 161 Eastern Road.
Topping Out | NEXTDC M2 Melbourne Stage 6
Earlier this week we celebrated the topping out of Stage 6 at NEXTDC’s M2 Melbourne Data Centre.